Shenango Act 2

On November 14, DEP received a response to its technical deficiency letter. The department has until February 18, 2020 to review and make a determination on the information received.

On July 15, 2019, DEP issued a technical deficiency letter following a review of the a Remedial Investigation Report (RIR), Risk Assessment, Cleanup Plan and Final Report submitted for the former Shenango Coke Plant. A response by the applicant is due within 60 days of the date on the letter.

On April 24, 2019, DEP received a Remedial Investigation Report (RIR), Risk Assessment, Cleanup Plan and Final Report for the former Shenango Coke Plant. DEP is currently reviewing these submissions.